Thursday, July 29, 2010

The Thompson Flats- So Close...

The condos at 2106 10th st are really moving along. We have most of the big stuff done, and we should be complete within three weeks. The plumbers are working in the house now to put in the toilets and faucets. Next week, the house will be basically empty as the floor crew comes in to stain the floors and apply the polyurethane.

In the pictures below, you can really see how much natural light there is in the building. None of the electric lights were turned on for the photos

The front windows are totally wrapped in the metal. The dark brown looks awesome with the white.


We poured the concrete for the front walkways earlier this week. Next week we need to get fill dirt to put in the two planters.


All of the master bedroom closets received Elfa storage systems from the Container Store.


The built-in shelves were completed last week around all of the gas fireplaces. We ordered glass tile to surround the fireplace and it should be in next week.


The master bathrooms all have wall-mounted floating vanities.



Here are the floors on the first floor. The cabinets are all wrapped in paper and plastic to protect them during construction.


The top loft area has a ton of light.



This is the color that we are staining the floors. It's a dark coffee/ebony mix.