The Thompson Flats- A few weeks away

We're almost done with this condo building. There is a lot of activity going on in the building, and each day it looks a little closer to being a home.

The crane came yesterday and dropped off the AC units for the roof. We set them as far back as possible so they aren't visible from the street.


The floor guys have been working really hard to prep the floor in order to stain and finish it. Today we tested out a variety of colors in order to choose the perfect stain.




Ever wonder how many electricians it takes to set up two pendant lights and four sets of track lighting per floor?


We finally got temporary power at the project. It was nice to see the place lit up, finally.



Tomorrow is a huge day because the countertops will be installed. I'll post more pictures after they are in.