Thursday, June 24, 2010

The Thompson Flats- Decks

At the 10th St project we have the building all ready to sheetrock and we're working to finish up several of the exterior projects. In the rear, we got most of the metal in place for the decks. Tomorrow, the carpenters will put in the handrails, and we should have the spiral done by the middle of next week. My welder is going to Africa for the entire month of July, so let's hope he finishes next week. All of my inspections are done and we have the go ahead to close-in the building. It took them almost 4 hours today with a crane to get the sheetrock on each floor, and the hanging crew claims they'll hang 500 sheets tomorrow and finish in one day. I'll believe it when I see it, but they do move fast. The taping and mudding takes about another week, so I hope to start trim and unfinished flooring at the beginning of the following week.