Friday, March 2, 2012

The Thompson- A few weeks left!

At The Thompson at 2108 10th St NW, our crews are hard at work finishing the trim and hanging all the doors.  We've also started on the tile work, and the roofer is finishing up small details on the roof.  Tomorrow, our painters will be priming all the walls.  We will be installing the cabinets and floors in about two weeks and aim to be on the market for the first week in April.


The back is all ready for the stairs and decks, which we're going to begin next week.
Camillo works to hang the doors on the first floor.


In the penthouse, the baseboards are finished and ready for hardwood floors.

In the penthouse, the steps are also all trimmed out.
 
Here, our tile subcontractor works to lay the tile in the loft bath.


The Homasote has all been delivered and will be installed next week.