Saturday, March 31, 2012

1120 Rhode Island Ave- Almost at Sheetrock

*Reminder- please update your bookmarks to http://lock7development.com/blog/ to continue reading all the newest posts from Lock 7 Development.  Thanks!

At The Newport Tower, we're moving along and aiming to have the Sheetrock installed by April 15th.  We're right on track, and we're finishing up the electric and the sprinklers this week.  The basement concrete is all poured and we're framing out that floor today and Monday.

This might look similar to past photos, but if you look closely, you'll see all the progress with the electric, plumbing and sprinklers.

On the side of the building, we dug out the new areaway to access the lower level.  Fortunately, the plumbing to the street runs in the same spot, so we were able to accomplish both tasks at the same time.