| We began removing the old windows to get ready for the new wood windows that are coming in later this week. |
| Inside, the floor installers worked to remove damaged flooring and patch floor pieces that were in better condition. |
| The crew worked diligently to tooth the new pieces in so the seams are invisible. |
| The flooring that they used for repairs were pieces we removed from elsewhere in the building, such as in the new hallway and the bathrooms. |
| The plumbers were also here today to run the new pipes. |
| The carpenters had to take a break from framing windows in order to remove some old plaster. Check out how big the windows are in this building. |
| The turret in the penthouse is fully framed and is incredible. |
| In the back penthouse unit, the balcony windows are all framed and ready for installation. |
| This building has all sorts of incredible original details, like the brick here. |
| The new steps are in place. |