Construction Progress- The Gracie at 1470 Chapin Rd

We're on track to finish 1470 Chapin Rd during the first week in March.  There's a lot going pretty much everywhere at the project.  Here are the current tasks:


In the back yard, the masons finished the retaining wall around the ground floor patio, and finished casting the posts in concrete.

Here's what the patio looks like now that the dirt has been graded back up against the retaining wall.

This morning, the crew worked to get the concrete footer poured for the new spiral steps .

Inside, the welder came over the weekend to install the inside rails in the top unit.

We have so much painting to finish that there are two separate crews working in the building.  One crew is finishing units 1 and 4 and the other is working in units 2 and 3.


The bedrooms are finished.