Lots going on at The Gracie project at 1470 Chapin St NW.  We're almost done with framing out the roof, which will be a big relief because the weather is starting to get wintery and we might get snow at the end of this week.


The water service contractor cut the street to run the new pipes for the water and sewer service.  We have to upgrade the size of the line at every condo project because of the increased demand.

The masons started repairing the brick in the front and building the walls of the new front balcony.  The new brick is the same size as the original, although the color is much darker.  This won't matter, though, once we paint the building.

This is the penthouse unit before the carpenters started working on the roof.  It's really, really cold outside.