The Thompson Flats- Closer to Sheetrock

The 10th St project is looking great. The plumbing, brick, electric and HVAC work are all about 50% complete, and should be 100% done by the end of the week. Next week we'll insulate and do final framing, so in about two weeks we will have the sheetrock up. That's the best part of the project because you can finally see the walls and layout.

Here's the wall along the alley where the brick is going up. The four masons go about 5 lines higher each day. Luckily all the masons from the other side of the house will now be working here, so this wall should really go up quick.


This is the completed block wall on the other side of the house. This week my goal is to paint it, weather permitting.


Inside, the tradesman are working. There are always tricky areas where the ducts and plumbing intersect, so this work can be tedious. Luckily in new construction there are fewer surprises.



Here's the model for the kitchens. They look amazing. Very sharp and modern. We are ordering them this week.