We are making incredible progress on all three of our current developments.  At The Thompson, the big push for last week and the one upcoming is to get the exterior work finished.  We are nearly done framing out the roof and finishing the brick work in the front and back.  Our roofer returns from a trip back to El Salvador on February 1st, and we'll have him get to work the next day on the front and rear metal details.

While the plumber is able to work before the building is completely water tight, both the electrician and HVAC contractors can not start until the building is 100% sealed up.  They should begin at the end of this week or the beginning of next.

In the front, the masons worked this week to install the front brick wall.  The brick is from the same factory as The Thompson Flats next door and looks nearly identical.

Here's the view from across the street.

In the rear, we worked this week to install the doors and windows so the masons could work.

No comments:

Post a Comment

 

© 2010. All Rights Reserved. | Custom Blog Design By Penny Lane Designs